PHASE 1 … A diagram provided by the Village of Swanton shows where in the village work will begin for Phase 1 and how that area will be affected.
By: Jacob Kessler
The Swanton Sewer Separation Project, known as project 8 and 9, will begin three weeks early. The contractor for this project notified the Swanton Village of their intent to begin work for this project on March 28th, weather permitting.
Road work will take place in four phases and will continue until Summer of this year. Phase 1 will begin on W. Garfield between Browning and Munson.
The work will include roadway excavation, installation of stone base and concrete curbs. During this phase there will be no parking permitted on W. Garfield, between Browning and Munson.
W. Garfield will be one way traffic, westbound from Elton’s Parkway to Browning and closed from Browning to Munson; W. Garfield will remain two-way between Elton’s Parkway and Main Street.
Complete details and updates on timelines will be posted on the village’s website throughout the remainder of the project.