The Bryan Board of Public Affairs met in a regular session on Monday, Aug. 24, at 5 p.m. and was updated on recommendations concerning the Auglaize Hydroelectric Plant, which is located on the Auglaize River in Defiance.
Director of Utilities Derek Schultz presented a high-level overview of a recent study and objectives on the plant completed by Thompson HCMS (Hydro Consulting and Maintenance Services) of Sumter, South Carolina.

The study was designed to evaluate current facility conditions, identify any reliability concerns and opportunities to increase generation, and determine how to optimize operations.
In addition to the study, Bryan Municipal Utilities (BMU) has to develop a long-term maintenance strategy as well as a long-term capital investment plan to identify some of the capital priorities for BMU.
“We are asking for high-level financial consideration for some of the recommended improvements,” Schultz said.
Schultz said the original dam was constructed in 1912, while the original powerhouse was decommissioned in 1962. It was reopened in the 1980s, and in 1996 the BPA approved buying it for $1.2 million.
He also told board members the plant continues to operate today, but much of the equipment is several decades old. There are six generating units inside the plant with a combined capacity of 4.7 megawatts.
One of the major findings was to identify the best way to move forward with one of the two biggest units, unit three, which has been out of commission for about two and a half years.
“Unit number three represents the greatest concern,” Schultz said. “Unit number three is currently in a forced outage. It’s inoperable.”
The study also provided three alternatives after evaluation of unit three.
-Base refurbishment, which would cost $1.78 million.
-Comprehensive refurbishment, which would cost $2.2 million.
-Purchasing all new equipment, which would cost $4.2 million but also had the worst estimated return on investment.
“They did recommend the complete refurbishment, and this is assuming all mechanical components will require machining or replacement,” Schultz said.
Bryan Power Plant Superintendent Jim Coressel said that under the comprehensive refurbishment, the parts will be pulled out and repaired and then put back in with the assistance of lasers to make sure they’re straight.
The recommendation is to fix unit three first, then once it’s back up and running, to take unit two offline and have it receive the same treatment as unit three.
Included in that is a recommendation for pond-level controls to automatically optimize the water levels to maximize available head pressure. Currently, these measures are taken manually.
The cost for that is estimated at $200,000 but is also expected to have the biggest return on investment (38 percent), with an estimated generation increase of 10 percent or 880 megawatt-hours per year.

Consultant Study Conclusions
-Overall assessments were positive.
-Facility is in satisfactory condition for its age.
-Six reliable generating units are achievable.
-Major investments concentrated in the first two years.

-Long-term maintenance needs become manageable.
-The facility can continue providing renewable generation for 20-plus years and help offset purchased power costs.
No action was taken following the study, but Schultz said he would be seeking direction from the board on how to proceed.
Other Business
-Charlotte Knisely was introduced to the BPA as the new public communications manager for Bryan Municipal Utilities.
With no further action, the meeting adjourned at 5:32 p.m. The next meeting will be on Monday, Sept. 14, at 5 p.m.